Thursday, 1 November 2007

Thursday, 1st November - It's all happening!

The radiators in the chancel have now been connected to the new heating pipework and are being switched on and tested today.

The joiners are completing the studding work for the tea-bar area and the electrician is doing all the first fixings to the area.

The painting has been finished, except for touching up at the end of the project.
The under floor heating work will begin on Monday Nov 5th, but the Even Heat engineer arrived this morning to install the manifolds ready.



Please note that the completion of the drainage has been delayed by Severn Trent until November 12th.

More updates will follow as changes occur, but may be infrequent over the next couple of weeks.

No comments: